The Bullwhip Comes for the Power Grid

 What the semiconductor industry can teach us about forecasting AI's electricity demand, where the lesson stops working, and who should carry the risk

On Thursday, I watched the Brookings webcast “AI and energy costs: Market and policy solutions.” One remark from the panel stuck with me: the forecasting of AI-driven electricity demand has not been good. That is true, but it should not surprise anyone. Forecasting is hard for any supplier at the bottom of a long value chain, and power companies now sit at the very bottom of a chain that ends with someone, somewhere, asking a chatbot a question.

I have seen this pattern before, in semiconductors and memory. The parallel explains a lot about why the forecasts are bad. It also breaks down in a few important places, and those are exactly the places that tell us what the fix should be.

The parallel: semiconductors at the base of the chain

Chipmakers and memory makers sit at the base of a value chain that ends with an electronic device on a retail shelf. Small swings in end demand turn into large swings in orders by the time they reach the fab. Supply-chain people call this the bullwhip effect.

The customers make it worse, and for rational reasons. A device maker that can't ship because it ran short of a $2 component loses far more than the cost of the component. So it orders more than it needs, sometimes from several suppliers at once, and lets the supplier sort it out. The 2020–2023 chip shortage was a textbook case: duplicate orders and padded forecasts created false demand signals, and by 2023 they had turned into excess inventory and cancelled orders.

Now look at the power grid. The data center developer is the device maker. It must deliver “intelligence” to AI companies, which must deliver it to end users, and nobody wants to be the one who can't deliver because the power wasn't there. So developers file requests with several utilities while they decide where to build. Industry estimates put interconnection requests at five to ten times the number of data centers that actually get built. Exelon has said only about 22% of its 65-gigawatt pipeline through 2040 is likely to materialize. The industry has a name for this: phantom data centers.

Until demand settles, that uncertainty flows down the chain to the power companies, just as it flowed down to the fabs.

How the chip industry is fixing it

The memory industry is now responding in a way that is salient for this debate. Samsung, SK Hynix and Micron are moving customers onto binding long-term        agreements of up to five years, often with large prepayments. Samsung has reportedly discussed more than $10 billion in prepayments from Microsoft, with any shortfall in purchased volume deducted from that payment.

That changes the forecast itself, not just who pays when it is wrong. An order that costs nothing to place carries little information. An order backed by a prepayment that the buyer forfeits if it doesn't buy is a forecast the buyer has priced. Commitment turns cheap talk into a credible signal.

Where the parallel breaks

If the power industry simply copied the chip industry, we would be most of the way there. But the analogy fails in three places, and each one matters.

1. Who absorbs the error. When chip customers over-order, the pain falls mostly on the supplier's shareholders and on the customers stuck with inventory. Regulated utilities are different. Their costs can be passed through to captive retail customers who never placed an order. In the PJM region, the market monitor has estimated that existing and projected data center growth added more than $23 billion to capacity-market costs across three auctions. Households pay for the speculation either way: through higher prices when supply is tight now, or through stranded-asset charges later if a utility builds for demand that never arrives. Utility shareholders are in a bind too. If they build and the load doesn't come, they take the hit, and regulators may end up raising rates to keep them whole.

2. Asset life versus forecast horizon. A memory agreement of three to five years roughly matches the technology cycle it covers. A gas plant takes years to build and runs for thirty or more. Even the best-informed customer, a hyperscaler with real visibility into its own compute demand, can credibly forecast only a few years ahead. No one can honestly commit to thirty years of AI demand.

3. Interchangeability. Excess chips can be sold to someone else at a discount. A power plant built next to a rural data center campus has a much narrower set of buyers for its output. A grid-connected plant can serve the wider system, but only if it was sited with that in mind.

The solution: put the risk where the information is

The organizing principle is simple: forecasting risk should sit with the party that has the best information about end demand and the balance sheet to carry it. That is not the residential ratepayer, and it isn't the utility either. It is the hyperscaler.

Concretely, I would propose four things.

•      A hyperscaler guarantee, not an AI-lab guarantee. Microsoft, Google, Amazon and Meta can credibly guarantee the debt a utility takes on to build generation for them, either directly or through the data center operator. Most AI labs cannot: they are burning cash, and they often rent compute from intermediaries who rent space from developers. A chain of guarantees is only as strong as its weakest link, and an AI lab's guarantee is weakest in the exact scenario where it would be called: AI demand falling short.

•      Let the utility build and operate. Google does not need to run a power plant. That's not its core competency. A guarantee lets the utility finance, build and operate the generation at a utility's cost of capital, while the hyperscaler carries the demand risk it is best placed to judge. Meta and Entergy Louisiana are already testing this model: Entergy is building gas plants for Meta's Louisiana campus under a 15-year supply contract, and Meta announced plans in March 2026 for seven more.

•      Make the commitment binding enough to clean up the queue. Many states already require large-load tariffs with minimum bills of 80–90% of contracted capacity, multi-year terms, collateral and exit fees. These do the same screening job as the memory makers' prepayments, and they should become the norm nationally.

•      Close the duration gap explicitly. This is the hard part. The Meta–Entergy deal shows it: critics point out that ratepayers could be left holding the plants after 15 years if Meta no longer needs the power. Assuming the country will need the power after the contract ends is a reasonable national bet. I would put fairly high odds on it. But a contract shouldn't depend on that assumption. Instead, front-load cost recovery so most of the plant is paid down within the guarantee period. Price whatever value remains in year 16 the way aircraft lessors price residual value. Site plants where the wider grid can use them, and use shorter-lived assets such as batteries or modular generation where the forecast horizon is short.

The honest forecast

Strategically, the best demand forecast available isn't any utility's load study. It is the number of years a hyperscaler is willing to put its own balance sheet behind. That number tells you what the best-informed party actually believes. A good contract makes that number visible, ties the price of the power to it, and pays down most of the risk before it can reach the household that never asked for a data center down the road.

The chip industry learned this lesson through a painful boom and bust. The power industry can learn it from them, but only if it remembers that its customers can't walk away from the bill.